P, Q and R can complete a work in 10, 12 and 15 days respectively. Only P works on the first day, only Q on the second day and only R on the third day; Then this cycle repeats. In how many days will the work be completed?

  1. 10 days
  2. 14 days
  3. 12 days
  4. 8 days
Answer and detailed solution are available in the protected study screen.