DSSSB · Mathematics

A can complete a work in 12 days and B can complete it in 6 days. They work together for the first 2 days. Then B leaves the work and A continues to work alone till the work is completed. How many total days did it take to complete the work?

  1. 6 days
  2. 8 days
  3. 10 days
  4. 2 days