DSSSB · Mathematics
M and S can complete a work in 18 days and 12 days respectively. They started the work together and after 4 days S left the work. In how many days can M alone complete the remaining work?
- 7 days
- 6 days
- 8 days
- 9 days
M and S can complete a work in 18 days and 12 days respectively. They started the work together and after 4 days S left the work. In how many days can M alone complete the remaining work?
- 7 days
- 6 days
- 8 days
- 9 days
Answer and detailed solution are available in the protected study screen.