DSSSB · Mathematics

Aman can do 1/4th of a work in 10 days and Chaman can do 1/6th of the same work in 14 days. If both work together, how many days will it take to complete the work? (Round the answer to one decimal place.)

  1. 27.1
  2. 24.1
  3. 30.7
  4. 21.1
Answer and detailed solution are available in the protected study screen.
Register or login to attempt