DSSSB · Mathematics

A can complete a work in 10 days and B can complete it in 15 days. They work together for the first 3 days. Then B leaves the work and A works alone till the work is completed. How many total days will it take to complete the work?

  1. 16
  2. 10
  3. 5
  4. 8
Answer and detailed solution are available in the protected study screen.
Register or login to attempt